# Sub-Division Number of Applications 11kV Min Duration(Days)11kv Max Duration(Days)11kv Average Duration(Days)11kv Applications Processed(%) 11kV
1 NAGALAPURAM 2 11.96 13.79 12.87 100.00
2 NAGARI 1 6.95 6.95 6.95 100.00