Processing of application for New Services / Additional Loads where network expansion required in APSPDCL - 11kV October-2021 To December-2021
# Sub-Division Number of Applications 11kV Min Duration(Days)11kv Max Duration(Days)11kv Average Duration(Days)11kv Applications Processed(%) 11kV
1 CHITTOOR CCO 1 13.88 13.88 13.88 100.00
2 CHITTOOR RURAL-3 2 7.88 14.87 11.38 100.00
3 CHITTOOR TOWN 2 10.9 13.89 12.39 100.00
Total 5 7.88 14.87 12.28 100.00