Processing of application for New Services / Additional Loads where network expansion required in APSPDCL - 11kV January-2022 To March-2022
# Sub-Division Number of Applications 11kV Min Duration(Days)11kv Max Duration(Days)11kv Average Duration(Days)11kv Applications Processed(%) 11kV
1 CHITTOOR RURALS 1 1 8.7 8.7 8.7 100.00
2 PAIPALLE 1 6.7 6.7 6.7 100.00
3 PALAMANER 1 9.83 9.83 9.83 100.00
Total 3 6.7 9.83 8.41 100.00