Processing of application for New Services / Additional Loads where network expansion required in APSPDCL - 11kV October-2021 To December-2021
# Division Number of Applications 11kV Min Duration(Days)11kv Max Duration(Days)11kv Average Duration(Days)11kv Applications Processed(%) 11kV
1 GUDUR 2 12.88 12.9 12.89 100.00
2 KAVALI 2 13.88 14.89 14.39 100.00
3 NAIDUPETA 1 14.9 14.9 14.9 100.00
4 NELLORE RURALS 2 2.88 6.89 4.88 100.00
Total 7 2.88 14.9 11.32 100.00