Processing of application for New Services / Additional Loads where network expansion required in APSPDCL - 11kV July-2021 To September-2021
# Division Number of Applications 11kV Min Duration(Days)11kv Max Duration(Days)11kv Average Duration(Days)11kv Applications Processed(%) 11kV
1 GUDUR 1 14.75 14.75 14.75 100.00
2 KAVALI 2 11.25 14.37 12.81 100.00
3 NELLORE RURALS 1 14.09 14.09 14.09 100.00
4 NELLORE TOWN 3 14.02 26.09 18.3 66.67
Total 7 11.25 26.09 15.62 85.71