# | Sub-Division | Number of Applications 11kV | Min Duration(Days)11kv | Max Duration(Days)11kv | Average Duration(Days)11kv | Applications Processed(%) 11kV |
---|---|---|---|---|---|---|
1 | NELLORE TOWN III | 1 | 86.91 | 86.91 | 86.91 | 0.00 |
2 | NELLORE TOWN-I | 1 | 26.87 | 26.87 | 26.87 | 0.00 |
3 | NELLORE TOWN-II | 1 | 22.96 | 22.96 | 22.96 | 0.00 |
Total | 3 | 22.96 | 86.91 | 45.58 | 0.00 |