Processing of application for New Services / Additional Loads where network expansion required in APSPDCL - 11kV October-2021 To December-2021
# Section Number of Applications 11kV Min Duration(Days)11kv Max Duration(Days)11kv Average Duration(Days)11kv Applications Processed(%) 11kV
1 KOVUR TOWN 1 14.89 14.89 14.89 100.00
Total 1 14.89 14.89 14.89 100.00