Processing of application for New Services / Additional Loads where network expansion required in APSPDCL - 11kV January-2022 To March-2022
# Sub-Division Number of Applications 11kV Min Duration(Days)11kv Max Duration(Days)11kv Average Duration(Days)11kv Applications Processed(%) 11kV
1 KALIGIRI 1 13.7 13.7 13.7 100.00
2 KOVUR 2 4.83 11.91 8.37 100.00
Total 3 4.83 13.7 10.14 100.00