Processing of application for New Services / Additional Loads where network expansion required in APSPDCL - 11kV January-2022 To March-2022
# Sub-Division Number of Applications 11kV Min Duration(Days)11kv Max Duration(Days)11kv Average Duration(Days)11kv Applications Processed(%) 11kV
1 ADONI 1 5.95 5.95 5.95 100.00
Total 1 5.95 5.95 5.95 100.00