Processing of application for New Services / Additional Loads where network expansion required in APSPDCL - 11kV July-2022 To September-2022
# Division Number of Applications 11kV Min Duration(Days)11kv Max Duration(Days)11kv Average Duration(Days)11kv Applications Processed(%) 11kV
1 KADAPA 1 13.23 13.23 13.23 100.00
2 PULIVENDULA 1 39.67 39.67 39.67 0.00
3 RAYACHOTY 1 0.12 0.12 0.12 100.00
Total 3 0.12 39.67 17.67 66.67