Processing of application for New Services / Additional Loads where network expansion required in APSPDCL - 11kV October-2021 To December-2021
# Division Number of Applications 11kV Min Duration(Days)11kv Max Duration(Days)11kv Average Duration(Days)11kv Applications Processed(%) 11kV
1 ANANTHAPUR 5 6.88 14.88 11.49 100.00
2 HINDUPUR 6 3.89 16.88 11.72 83.33
3 KALYANDURG 2 9.88 9.9 9.89 100.00
Total 13 3.89 16.88 11.35 92.31