Processing of application for New Services / Additional Loads where network expansion required in APSPDCL - 11kV October-2021 To December-2021
# Sub-Division Number of Applications 11kV Min Duration(Days)11kv Max Duration(Days)11kv Average Duration(Days)11kv Applications Processed(%) 11kV
1 ANANTHAPUR EAST 1 12.88 12.88 12.88 100.00
2 ANANTHAPUR TOWN 2 3 9.9 14.88 12.55 100.00
3 ANANTHAPUR WEST 1 6.88 6.88 6.88 100.00
Total 5 6.88 14.88 11.49 100.00