Processing of application for New Services / Additional Loads from Existing Network in APSPDCL October-2021 To December-2021
# Section Number of Applications EN Min Duration(Days)EN Max Duration(Days)EN Average Duration(Days)EN Applications Processed(%) EN
1 K.V.B. PURAM 48 0.0 0.0 0.0 100.00
2 PAPANAIDUPETA 273 0.0 0.0 0.0 100.00
3 RURAL, SRIKALAHASTHI 203 0.0 0.0 0.0 100.00
4 YERPEDU OPERATION 101 0.0 0.0 0.0 100.00
Total 625 0.0 0.0 0.0 100.00