Processing of application for New Services / Additional Loads from Existing Network in APSPDCL April-2022 To June-2022
# Section Number of Applications EN Min Duration(Days)EN Max Duration(Days)EN Average Duration(Days)EN Applications Processed(%) EN
1 NAGARI OPERATION 101 0.0 0.0 0.0 100.00
2 NAGARI RURAL 68 0.0 0.0 0.0 100.00
3 NINDRA 41 0.0 0.0 0.0 100.00
4 PANNUR 29 0.0 0.0 0.0 100.00
Total 239 0.0 0.0 0.0 100.00