Processing of application for New Services / Additional Loads from Existing Network in APSPDCL Jan-2021 To Mar-2021
# Sub-Division Number of Applications EN Min Duration(Days)EN Max Duration(Days)EN Average Duration(Days)EN Applications Processed(%) EN
1 KALIKIRI 173 0.0 0.0 0.0 100.00
2 PILER CCO 196 0.0 0.0 0.0 100.00
3 PILER RURALS 150 0.0 0.0 0.0 100.00
Total 519 0.0 0.0 0.0 100.00