Processing of application for New Services / Additional Loads from Existing Network in APSPDCL October-2021 To December-2021
# Section Number of Applications EN Min Duration(Days)EN Max Duration(Days)EN Average Duration(Days)EN Applications Processed(%) EN
1 MADANAPALLI EAST 169 0.0 0.0 0.0 100.00
2 MADANAPALLI NORTH 122 0.0 0.0 0.0 100.00
3 MADANAPALLI TOWN 248 0.0 0.0 0.0 100.00
4 MADANAPALLI WEST 147 0.0 0.0 0.0 100.00
Total 686 0.0 0.0 0.0 100.00