Processing of application for New Services / Additional Loads from Existing Network in APSPDCL October-2021 To December-2021
# Sub-Division Number of Applications EN Min Duration(Days)EN Max Duration(Days)EN Average Duration(Days)EN Applications Processed(%) EN
1 MADANAPALLE 686 0.0 0.0 0.0 100.00
2 MADANAPALLE RURAL1 372 0.0 0.0 0.0 100.00
3 MADANAPALLE RURAL2 356 0.0 0.0 0.0 100.00
4 PUNGANUR 468 0.0 0.0 0.0 100.00
Total 1882 0.0 0.0 0.0 100.00