Processing of application for New Services / Additional Loads from Existing Network in APSPDCL October-2022 To December-2022
# Section Number of Applications EN Min Duration(Days)EN Max Duration(Days)EN Average Duration(Days)EN Applications Processed(%) EN
1 ARAGONDA 44 0.0 0.0 0.0 100.00
2 IRALA OPERATION 42 0.0 0.0 0.0 100.00
3 IRALA RURALS 51 0.0 0.0 0.0 100.00
4 PAIPALLE 52 0.0 0.0 0.0 100.00
Total 189 0.0 0.0 0.0 100.00