Processing of application for New Services / Additional Loads from Existing Network in APSPDCL July-2022 To September-2022
# Sub-Division Number of Applications EN Min Duration(Days)EN Max Duration(Days)EN Average Duration(Days)EN Applications Processed(%) EN
1 CHITTOOR RURAL-I 255 0.0 0.0 0.0 100.00
2 PAIPALLE CCO 210 0.0 0.0 0.0 100.00
3 PALAMANER 568 0.0 0.0 0.0 100.00
Total 1033 0.0 0.0 0.0 100.00