Processing of application for New Services / Additional Loads from Existing Network in APSPDCL Jan-2021 To Mar-2021
# Sub-Division Number of Applications EN Min Duration(Days)EN Max Duration(Days)EN Average Duration(Days)EN Applications Processed(%) EN
1 CHITTOOR RURAL-I 187 0.0 0.0 0.0 100.00
2 PAIPALLE CCO 218 0.0 0.0 0.0 100.00
3 PALAMANER 275 0.0 0.0 0.0 100.00
Total 680 0.0 0.0 0.0 100.00