Processing of application for New Services / Additional Loads from Existing Network in APSPDCL Apr-2021 To Jun-2021
# Sub-Division Number of Applications EN Min Duration(Days)EN Max Duration(Days)EN Average Duration(Days)EN Applications Processed(%) EN
1 CHITTOOR RURAL-I 237 0.0 0.0 0.0 100.00
2 PAIPALLE CCO 196 0.0 0.0 0.0 100.00
3 PALAMANER 497 0.0 0.0 0.0 100.00
Total 930 0.0 0.0 0.0 100.00