Processing of application for New Services / Additional Loads from Existing Network in APSPDCL October-2021 To December-2021
# Sub-Division Number of Applications EN Min Duration(Days)EN Max Duration(Days)EN Average Duration(Days)EN Applications Processed(%) EN
1 NELLORE TOWN III 244 0.0 0.0 0.0 100.00
2 NELLORE TOWN-I 495 0.0 0.0 0.0 100.00
3 NELLORE TOWN-II 734 0.0 0.0 0.0 100.00
Total 1473 0.0 0.0 0.0 100.00