Processing of application for New Services / Additional Loads from Existing Network in APSPDCL July-2021 To September-2021
# Section Number of Applications EN Min Duration(Days)EN Max Duration(Days)EN Average Duration(Days)EN Applications Processed(%) EN
1 CHILLAKUR 112 0.0 0.0 0.0 100.00
2 GUDUR RURALS-I 49 0.0 0.0 0.0 100.00
3 GUDUR RURALS-II 44 0.0 0.0 0.0 100.00
4 GUDUR TOWN-I 70 0.0 0.0 0.0 100.00
5 GUDUR TOWN-II 104 0.0 0.0 0.0 100.00
Total 379 0.0 0.0 0.0 100.00