Processing of application for New Services / Additional Loads from Existing Network in APSPDCL October-2022 To December-2022
# Sub-Division Number of Applications EN Min Duration(Days)EN Max Duration(Days)EN Average Duration(Days)EN Applications Processed(%) EN
1 ATMAKURU 380 0.0 0.0 0.0 100.00
2 UDAYAGIRI 207 0.0 0.0 0.0 100.00
Total 587 0.0 0.0 0.0 100.00