Processing of application for New Services / Additional Loads from Existing Network in APSPDCL July-2021 To September-2021
# Section Number of Applications EN Min Duration(Days)EN Max Duration(Days)EN Average Duration(Days)EN Applications Processed(%) EN
1 B.PALLI (R) 85 0.0 0.0 0.0 100.00
2 B.PALLI (U) 127 0.0 0.0 0.0 100.00
Total 212 0.0 0.0 0.0 100.00