Processing of application for New Services / Additional Loads from Existing Network in APSPDCL Oct-2020 To Dec-2020
# Division Number of Applications EN Min Duration(Days)EN Max Duration(Days)EN Average Duration(Days)EN Applications Processed(%) EN
1 KADAPA 295 0.0 0.0 0.0 100.00
2 MYDUKUR 441 0.0 0.0 0.0 100.00
3 PRODDATUR 191 0.0 0.0 0.0 100.00
4 PULIVENDULA 66 0.0 0.0 0.0 100.00
5 RAJAMPET 418 0.0 0.0 0.0 100.00
6 RAYACHOTY 217 0.0 0.0 0.0 100.00
Total 1628 0.0 0.0 0.0 100.00