Processing of application for New Services / Additional Loads from Existing Network in APSPDCL July-2022 To September-2022
# Sub-Division Number of Applications EN Min Duration(Days)EN Max Duration(Days)EN Average Duration(Days)EN Applications Processed(%) EN
1 KALYANDURG HQ 194 0.0 0.0 0.0 100.00
2 KALYANDURG RURALS 124 0.0 0.0 0.0 100.00
3 RAYADURG 379 0.0 0.0 0.0 100.00
4 URAVAKONDA 254 0.0 0.0 0.0 100.00
Total 1852 0.0 0.0 0.0 100.00