Processing of application for New Services / Additional Loads from Existing Network in APSPDCL October-2021 To December-2021
# Section Number of Applications EN Min Duration(Days)EN Max Duration(Days)EN Average Duration(Days)EN Applications Processed(%) EN
1 TADIPATRI D1 129 0.0 0.0 0.0 100.00
2 TADIPATRI D2 241 0.0 0.0 0.0 100.00
3 TADIPATRI RURALS 81 0.0 0.0 0.0 100.00
4 YADIKI 79 0.0 0.0 0.0 100.00
Total 390 0.0 0.0 0.0 100.00