Category change requests effected in APSPDCL April-2022 To June-2022
# Section Number of Requests CC Min Duration(Days)CC Max Duration(Days)CC Average Duration(Days)CC Requests Handled(%) CC
1 BELLARY ROAD 78 0.1 11.09 3.45 96.15
2 CENTRAL SECTION 7 0.85 2.09 1.43 100.00
3 POWER HOUSE 5 1.97 9.92 6.6 40.00
4 SANTHOSH NAGAR 27 0.73 6.85 3.62 100.00
Total 117 0.1 11.09 3.77 84.04